Specify Assured Recovery Test Job Schedule
The schedule tab lets you specify the assured recovery test job schedule. If you do not specify a schedule, then the task starts immediately when you complete the primary task.
Follow these steps:
- Click the Schedule tab.
- Click Add, and then Add Assured Recovery Test Job Schedule.
- Add Assured Recovery Test Job Schedule dialog is displayed.
- Specify the schedule and click Save.
- The dialog closes and schedule tab displays the specified.
- Notes:
- If Assured Recovery source is Latest Recovery Points + Enable Assured Recovery schedule, the default value is 1. As a result, by default the latest one is verified.
- For value <=0, all unverified recovery points are tested.
- If Assured Recovery source is Daily/Weekly/Monthly + Enable Assured Recovery schedule, the default value is 9 (7 daily + 1 weekly + 1 monthly).
- For value <=0, all unverified recovery points are tested.
- If you do not want to use the default value, you can add a DWORD 32bit registry key at the following location:
- HKEY_LOCAL_MACHINE\SOFTWARE\Arcserve\Unified Data Protection\Engine\AssuredRecovery\MaxNumberOfRecoveryPoint