Modify a Staging Rotation Scheme

If you are using rotation or GFS rotation disk staging jobs, Arcserve Backup provides you with the flexibility to disable staging on any specified day of the week.

To modify staging when using a rotation scheme

  1. Open the Backup Manager and select the Schedule tab.
  2. Select the Use Rotation Scheme option, and then select the scheme name from the Scheme Name drop-down list.
  3. Click the Rotation Rules tab.

    The Staging column displays the current status of staging as it applies to your rotation scheme.

  4. Select the Day Of Week for which you want to modify staging, and then click the Modify button.

    The Configuration dialog opens.

  5. From the Staging drop-down list, select Enable or Disabled.
  6. Click OK.

Note: To disable staging for a staging group, see Disable Staging.