Specify Assured Recovery Test Job Schedule

The schedule tab lets you specify the assured recovery test job schedule. If you do not specify a schedule, then the task starts immediately when you complete the primary task.

Follow these steps:

  1. Click the Schedule tab.
  2. Click Add, and then select Add Assured Recovery Test Job Schedule.
  3. On the Add Assured Recovery Test Job Schedule dialog, do the following, and then click Save:
  4. The Assured Recovery test job is scheduled and appears on the Schedule page.
  5. Notes:
    • If Assured Recovery source is Latest Recovery Points + Enable Assured Recovery schedule, the default value is 1. As a result, by default the latest one is verified.
    • For value <=0, all unverified recovery points are tested.
    • If Assured Recovery source is Daily/Weekly/Monthly + Enable Assured Recovery schedule, the default value is 9 (7 daily + 1 weekly + 1 monthly).
    • For value <=0, all unverified recovery points are tested.

Next Step: