![Previous Topic: Configure Online Arcserve Replication Replication Scenario for Deduplication Devices](574.png)
![Next Topic: Back Up Data Using Global Deduplication](573.png)
Using Deduplication › Back up Data with Deduplication › How Staging Jobs Work with Deduplication › Configuration Considerations for Arcserve Replication Deduplication Device Scenarios › Configure Scheduled Arcserve Replication Replication Scenarios for Deduplication Devices
Configure Scheduled Arcserve Replication Replication Scenarios for Deduplication Devices
When you use scheduled replication for your deduplication device replication scenario, you must manually generate VSS Snapshots in order to restore data in case of device failure.
To configure scenarios for scheduled replication
- From the Arcserve Replication Manager, select the scenario you created to replicate the deduplication device.
- Click the Properties tab for this scenario.
- Set the Replication, Mode property to Scheduling.
- Schedule the replication time at 0:00 daily.
- From the Arcserve Replication Manager, select the Replica server.
- Click the Properties tab for this server.
- Set the Scheduled Tasks, Replica Integrity Testing for Assured Recovery, Action on successful test, Create Shadow Copy (VSS) property to On.
- Save the changes.
- Run the deduplication device replication scenario.
- Manually generate VSS Snapshots:
- Select the Replica server for the deduplication device replication scenario you created.
- Click the Replica Integrity Testing button on the Arcserve Replication Manager toolbar.
- When the Replica Testing for Assured Recovery screen opens, click OK to start.
Copyright © 2016 .
All rights reserved.
![Previous Topic: Configure Online Arcserve Replication Replication Scenario for Deduplication Devices](574.png) ![Next Topic: Back Up Data Using Global Deduplication](573.png)
|
|