Upgrade Sequence for UDP Console, RPS, and Agent

Based on the Backward Compatibility Support Policy, plan your upgrade in the following sequence to ensure the upgrade works smoothly:

  1. Upgrade Arcserve UDP Console.
  2. Upgrade Arcserve UDP RPS (DR site).
  3. Upgrade Arcserve UDP RPS (Data Center).
  4. Upgrade Arcserve UDP Agentless Proxy, some Agents in Data Center.
  5. Upgrade Arcserve UDP RPS (Remote site).
  6. Upgrade Arcserve UDP Agentless Proxy and some Agents at the remote site.

    Note: Repeat Step 5 and 6 for each remote location.

Note: Per the replication backward support policy, always upgrade the target RPS before the source RPS.