Verify the Plan

To verify the copy recovery points feature, confirm that you have successfully created the plan. After you verify that the plan is created successfully, check whether the backup job is running as scheduled. After the backup job successfully completes, the copy recovery points job runs. You can check the status of the backup job and the copy recovery points job from the jobs tab.

Follow these steps to verify plans:

  1. Click the resources tab.
  2. From the left pane, navigate to Nodes, and click All Nodes.

    A list of all nodes is displayed on the center pane.

  3. Verify that plans are mapped with nodes.

Follow these steps to verify copy recovery points jobs:

  1. Click the jobs tab.
  2. From the left pane, click All Jobs.

    The status of each job is listed on the center pane.